
Retaining Ellicott City's Historic Charm
Retaining Ellicott City's Historic Charm
Retaining Ellicott City's Historic Charm
Retaining Ellicott City's Historic Charm
Retaining Ellicott City's Historic Charm
Retaining Ellicott City's Historic Charm
Capital Projects Tracker
Phase 2 NEW!
Phase 2 NEW!
Calvin Ball
County Executive

Capital Projects Tracker
The capital projects tracker was created to provide the public with up-to-date information about the status of capital projects associated with County Executive Calvin Ball's flood mitigation plan. Each tracker shows the current status of the project, as well as an estimated completion year.
​
These timelines are aggressive and count on the cooperation of a variety of stakeholders. Many different factors can cause project delays, including weather, acquisition delays, and issues with permitting. If a project is delayed for any reason, information about that delay will be communicated here.
​
If you have any questions or concerns about the capital projects tracker, send an email to ecsafeandsound@howardcountymd.gov.
*PLEASE NOTE: The capital projects tracker can only be viewed on a desktop computer.
Safe and Sound Projects
H7 Pond A 13-acre-foot dry flood mitigation pond located in the US 40/US 29 interchange
ACQUISITION
COMPLETE
DESIGN
Final Design
Preliminary Design
COMPLETE
COMPLETE
PERMITTING
COMPLETE
BUILD
CURRENTLY UNDERWAY
COMPLETE
Bid Advertised
Construction Start
Quaker Mill Pond A 10-acre-foot dry flood mitigation pond located off Rogers Avenue
ACQUISITION
COMPLETE
DESIGN
Final Design
Preliminary Design
COMPLETE
COMPLETE
PERMITTING
COMPLETE
​
BUILD
CONSTRUCTION UNDERWAY
COMPLETE
Bid Advertised
Construction Start
Maryland Avenue Culvert One 8 foot by 12 foot box culvert installed under Maryland Avenue
ACQUISITION
COMPLETE
DESIGN
Final Design
Preliminary Design
COMPLETE
ONGOING
PERMITTING
EXPECTED COMPLETION
6/2022
BUILD
Expected 12/2022
5/2022
CMAR Advertised
Construction Start
Extended North Tunnel A 15-foot diameter tunnel extending from the West End to the Patapsco River
ACQUISITION
IN PROGRESS
DESIGN
Final Design
Preliminary Design
COMPLETE
Expected Completion 9/2022
PERMITTING
EXPECTED COMPLETION
9/2022
BUILD
Expected 11/2022
COMPLETE
CMAR Advertised
Construction Start
NC3 Pond A 63-acre-foot dry flood mitigation pond located in the Autumn Branch of the New Cut Watershed
ACQUISITION
IN PROGRESS
DESIGN
Final Design
Preliminary Design
COMPLETE
Expected Completion 10/2023
PERMITTING
EXPECTED COMPLETION
10/2023
BUILD
3/2024
12/2023
Bid Advertised
Construction Start
H4 Pond A 15.6-acre-foot dry flood mitigation pond located on the Hudson Branch
ACQUISITION
COMPLETE
DESIGN
Final Design
Preliminary Design
COMPLETE
Expected Completion 1/2023
PERMITTING
EXPECTED COMPLETION
1/2023
BUILD
Expected 4/2023
1/2023
Bid Advertised
Construction Start
Additional Projects*
Partial Removal of County-Owned Buildings Removal of portions of county-owned buildings on Main St. that are over the stream channel
ACQUISITION
COMPLETE
PERMITTING
ONGOING
BUILD
Expected 9/2022
N/A
Bid Advertised
Construction Start
DESIGN
Final Design
Preliminary Design
COMPLETE
COMPLETE
Full Removal of County-Owned Buildings Removal of county-owned buildings on Main Street
ACQUISITION
COMPLETE
PERMITTING
EXPECTED COMPLETION
8/2022
BUILD
Expected 9/2022
N/A
Bid Advertised
Construction Start
DESIGN
Final Design
Preliminary Design
COMPLETE
COMPLETE