top of page
incl_process.png

Capital Projects Tracker

The capital projects tracker was created to provide the public with up-to-date information about the status of capital projects associated with County Executive Calvin Ball's flood mitigation plan. Each tracker shows the current status of the project, as well as an estimated completion year.

​

These timelines are aggressive and count on the cooperation of a variety of stakeholders. Many different factors can cause project delays, including weather, acquisition delays, and issues with permitting. If a project is delayed for any reason, information about that delay will be communicated here. 

​

If you have any questions or concerns about the capital projects tracker, send an email to  ecsafeandsound@howardcountymd.gov.

 

*PLEASE NOTE: The capital projects tracker can only be viewed on a desktop computer.

Safe and Sound Projects

H7 Pond A 13-acre-foot dry flood mitigation pond located in the US 40/US 29 interchange

New Single - Artist Name
00:00 / 00:00
ACQUISITION

COMPLETE

New Single - Artist Name
00:00 / 00:00
DESIGN

Final Design

Preliminary Design

COMPLETE

COMPLETE

New Single - Artist Name
00:00 / 00:00
PERMITTING

COMPLETE

New Single - Artist Name
00:00 / 00:00
BUILD

COMPLETE

COMPLETE

Bid Advertised

Construction

Quaker Mill Pond A 10-acre-foot dry flood mitigation pond located off Rogers Avenue

ACQUISITION

COMPLETE

DESIGN

Final Design

Preliminary Design

COMPLETE

COMPLETE

PERMITTING

 

COMPLETE

​

BUILD

COMPLETE

COMPLETE

Bid Advertised

Construction

ONGOING

Maryland Avenue Culvert One 8 foot by 12 foot box culvert installed under Maryland Avenue

ACQUISITION

COMPLETE

DESIGN

Final Design

Preliminary Design

COMPLETE

ONGOING

PERMITTING

ONGOING

BUILD

TBD

COMPLETE

CMAR Advertised

Construction Start

Extended North Tunnel A 18-foot diameter tunnel extending from the West End to the Patapsco River

ACQUISITION

IN PROGRESS

DESIGN

Final Design

Preliminary Design

COMPLETE

Ongoing

PERMITTING

ONGOING

BUILD

TBD

COMPLETE

CMAR Advertised

Construction Start

NC3 Pond A 63-acre-foot dry flood mitigation pond located in the Autumn Branch of the New Cut Watershed

ACQUISITION

IN PROGRESS

DESIGN

Final Design

Preliminary Design

COMPLETE

Ongoing

PERMITTING

ONGOING

BUILD

TBD

TBD

Bid Advertised

Construction Start

H4 Pond A 15.6-acre-foot dry flood mitigation pond located on the Hudson Branch 

ACQUISITION

COMPLETE

DESIGN

Final Design

Preliminary Design

COMPLETE

Ongoing

PERMITTING

ONGOING

BUILD

TBD

TBD

Bid Advertised

Construction Start

Additional Projects* 

Partial Removal of County-Owned Buildings Removal of portions of county-owned buildings on Main St. that are over the stream channel

ACQUISITION

COMPLETE

PERMITTING

ONGOING

BUILD

TBD

N/A

Bid Advertised

Construction Start

DESIGN

Final Design

Preliminary Design

COMPLETE

COMPLETE

Full Removal of County-Owned Buildings Removal of county-owned buildings on Main Street

ACQUISITION

COMPLETE

PERMITTING

ONGOING

BUILD

TBD

N/A

Bid Advertised

Construction Start

DESIGN

Final Design

Preliminary Design

COMPLETE

COMPLETE

*Complimentary projects that are not included in the list of Safe and Sound projects.

Frequently Asked Questions

bottom of page